Over 30 Days in Final Testing Phase Eglinton Crosstown LRT Evaluation Continues

ago 3 hours
Over 30 Days in Final Testing Phase Eglinton Crosstown LRT Evaluation Continues

The Eglinton Crosstown Light Rail Transit (LRT) system is currently in its final testing phase, following a rigorous evaluation process that began over 30 days ago. This demonstration aims to test the system’s readiness for revenue service without public access.

Current Status of Eglinton Crosstown LRT Testing

On October 7, 2023, Metrolinx, the provincial transit agency, announced the start of its revenue service demonstration (RSD) for the Eglinton Crosstown LRT. This 30-day testing period simulates full operations, including regular schedules and stops, while keeping the line closed to passengers.

Timeline and Incident Details

The initial plan was for testing to conclude around November 6, 2023. However, an incident occurred in late October during the testing phase. Metrolinx revealed that this incident took place during the unscored testing portion, allowing the evaluation to continue without resetting the timeline.

  • Start of RSD: October 7, 2023
  • Expected end of RSD: November 6, 2023
  • Incident occurred: Late October 2023

Phased Testing Approach

Metrolinx has divided the RSD into two distinct phases: unscored and scored testing. The unscored phase allows for operation without impacting the overall timeline, while issues during the scored phase would require a restart of that specific week’s testing.

Future Outlook

The agency has not disclosed how many days remain in the evaluation process. However, they have indicated that testing has now transitioned into the scored phase. Completion of the RSD will depend on the outcomes observed during this critical evaluation stage.

The Eglinton Crosstown LRT was initiated under a previous government and has been under construction for seven years. Originally, the opening date was repeatedly delayed, with former Metrolinx CEO Phil Verster announcing that a specific opening date would only be communicated three months prior to service commencement.

In recent developments, Metrolinx has adjusted this notice period to one month and aims for October 2023 to finalize testing. Comparatively, the Finch West LRT, which completed its RSD in late October, is slated to open on December 7, 2023. If the Crosstown LRT follows a similar timeline, its public service initiation could extend beyond this year.